Project 1 – after discovery of structural issues in two existing classroom buildings, a tenth campus was added to the first round of Prop O projects.
- Demolish 200 and 300 buildings.
- New two-story classroom building, food services, counseling center and library.
- Interim Housing
Webcam (username is “viewer” and password is “viewme”)
Architect – LPA, Inc.
Contractors –
- Balfour Beatty (lease/lease-back)
- Symbolic (interim housing)
Status –
- Interim Housing Classroom complete in 2010 and certified by DSA on 8/10/10.
- Interim Housing Restroom complete in 2010 and certified by DSA on 7/15/11.
- Interim Housing Library complete in 2011 and certified by DSA on 8/17/12.
- The new buildings were occupied for the start of school in July 2013 and certified by DSA on 12/10/14.