- Bonita Vista High, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 12/8/14.
- Bonita Vista Middle, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/13/15.
- Castle Park High, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 12/8/14.
- Castle Park Middle, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 12/5/14.
- Chula Vista High, TMAD Taylor-Gaines, Time and Alarm Systems, certified by DSA on 10/10/14.
- Chula Vista Middle, Ruhnau Ruhnau Clarke, Time and Alarm Systems, certified by DSA on 6/27/14.
- Eastlake High, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 11/25/14.
- Granger Jr. High, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/23/15.
- Hilltop High, Ruhnau Ruhnau Clarke, Time and Alarm Systems, certified by DSA on 8/28/14.
- Hilltop Middle, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/23/15.
- Montgomery High, Ruhnau Ruhnau Clarke, Time and Alarm Systems, certified by DSA on 8/28/14.
- Montgomery Middle, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/23/15.
- Mar Vista High, LPA, Standard Electronics, complete.
- Mar Vista Academy (Middle), Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/23/15.
- National City Middle, LPA, McCarthy Contractors, certified by DSA on 1/16/15.
- Palomar High, Johnson Consulting Engineers (JCE), Time and Alarm Systems, certified by DSA on 1/14/15.
- Southwest High, LPA, Standard Electronics, complete.
- Southwest Middle, BCA Architects, Standard Electronics, complete, certified by DSA on 5/15/14.
- Sweetwater High, BCA Architects, SUHSD staff, complete (non-DSA).