Montgomery MS

Project 1 – after discovery of structural issues in two existing classroom buildings, a tenth campus was added to the first round of Prop O projects.

  • Demolish 200 and 300 buildings.
  • New two-story classroom building, food services, counseling center and library.
  • Interim Housing

Webcam (username is “viewer” and password is “viewme”)

Architect – LPA, Inc.
Contractors –

  • Balfour Beatty (lease/lease-back)
  • Symbolic (interim housing)

Status –

  • Interim Housing Classroom complete in 2010 and certified by DSA on 8/10/10.
  • Interim Housing Restroom complete in 2010 and certified by DSA on 7/15/11.
  • Interim Housing Library complete in 2011 and certified by DSA on 8/17/12.
  • The new buildings were occupied for the start of school in July 2013 and certified by DSA on 12/10/14.