Track and Field –
Architect: NTD Architects
- This project is for the design of an artificial track and field, electrical infrastructure for stadium lights, bleachers and restrooms.
- This project was submitted to DSA on December 26, 2013 and approved on June 5, 2014
- Funding for construction has not been identified. The project is on HOLD
HVAC Upgrades –
Architect: NTD Architects
Contractor: M.A. Stevens
- This project added air conditioning to the 600 building and upgrade the units in the administration, library and counseling center
- Construction complete and certified by DSA on 5/12/14